VDOT and highway construction projects require contractors to follow detailed specifications, change procedures, documentation requirements, and claim deadlines. A contractor may have a legitimate basis for additional compensation or time and still lose the claim if the required notice or supporting records are missing.

Waldrop & Colvin helps contractors and subcontractors evaluate, document, preserve, negotiate, and pursue claims arising from Virginia highway and transportation construction projects.

Common VDOT Project Claims

  • Extra and changed work
  • Differing site conditions
  • Quantity and measurement disputes
  • Delay and disruption
  • Acceleration and resequencing
  • Utility and third-party interference
  • Plan and specification issues
  • Suspension and restricted access
  • Subcontractor pass-through claims

Legal Services for VDOT and Highway Contractors

We assist with active project issues, notices of intent to file a claim, change order disputes, claim preparation, subcontractor pass-through claims, administrative review, negotiation, and litigation.

📨

Notice of Intent Review

We help contractors identify when a written Notice of Intent to File a Claim may be required and prepare notices that clearly identify the occurrence, disputed work, and requested adjustment.

📝

Change Order Disputes

We assist when the parties agree that work changed but disagree about entitlement, pricing, time, quantities, markup, or the full impact of the change.

📅

Delay and Schedule Claims

We evaluate project schedules, contemporaneous updates, critical path effects, disruption, acceleration, extended performance, and time-related costs.

🧱

Differing Site Conditions

We help document and evaluate physical conditions that differ materially from contract indications or conditions ordinarily encountered in the work.

🔢

Quantity and Payment Disputes

We assist with disagreements involving measured quantities, pay items, unit-price work, eliminated items, acceptance, deductions, and final estimates.

🔁

Pass-Through Claims

We help subcontractors document claims for presentation through the prime contractor and address the prime contractor's obligations under the subcontract.

VDOT Claims Require More Than Proof of Additional Cost

A supported claim generally must establish a contractual basis for relief, actual impact, compliance with applicable notice and procedural requirements, and a reliable calculation of the requested adjustment.

Claim Element What the Contractor Must Address Examples of Supporting Evidence
Procedure The contractor must comply with applicable notice, recordkeeping, change order, schedule, certification, and claim submission requirements. Written notices, delivery records, acknowledgment letters, contract provisions, and claim certifications
Entitlement The contractor must identify a contract provision or other recognized basis allowing additional compensation, time, or another adjustment. Contract documents, specifications, special provisions, plans, directives, and change provisions
Impact The contractor must connect the disputed occurrence to increased cost, additional work, reduced productivity, or increased project time. Daily reports, schedules, photographs, correspondence, labor records, and equipment records
Causation The claimed impact must be separated from costs caused by the contractor, subcontractors, unrelated events, or existing project conditions. Schedule analysis, responsibility records, baseline comparisons, and contemporaneous project documents
Quantification The contractor must calculate the requested compensation or time using reliable and supportable information. Actual cost records, invoices, payroll, equipment records, quantity calculations, and schedule impact analysis

A contractor may have experienced a real financial loss but still need to establish each required element before VDOT will adjust the contract.

Notice of Intent to File a VDOT Claim

The Notice of Intent to File a Claim is a critical part of the VDOT claims process. It gives the Department early notice of an existing or impending claim and an opportunity to review, mitigate, or resolve the issue.

⏱️

When Notice May Be Required

A contractor generally must provide written notice at the time of the occurrence or before beginning disputed work upon which a claim for additional compensation or time will be based.

Separate contract provisions may impose additional notices for delay, differing site conditions, suspension, or other project events.

✍️

Express Written Notice

The notice should expressly state that it is a “Notice of Intent to File a Claim.” A field discussion, routine email, request for information, proposed change order, or verbal objection may not satisfy this requirement.

The contract should be reviewed to identify the correct recipient and method of submission.

📍

Identify the Occurrence

The notice should identify the project, contract, affected work, relevant date, disputed direction or condition, and the basis for anticipated additional compensation or time.

A broad reservation of all possible claims may not adequately identify the particular occurrence.

📊

Track Costs and Time

After providing notice, the contractor should separately track labor, materials, equipment, quantities, production, and schedule effects related to the disputed occurrence.

Records should be compared with project inspection records when required or practical.

A change order request is not necessarily a Notice of Intent to File a Claim. VDOT guidance distinguishes an NOI from other project notices and change-management documents. Contractors should separately satisfy each applicable requirement.

Common VDOT and Highway Project Claims

Highway construction claims often involve a combination of field conditions, contract interpretation, schedule effects, and contemporaneous project administration.

🔄

Changes to the Work

Changes may involve added or deleted pay items, modified scope, revised methods, plan changes, changed work hours, new restrictions, or other requirements different from those at bid.

🧱

Differing Site Conditions

Subsurface, physical, environmental, drainage, utility, or other conditions may materially differ from contract indications or conditions ordinarily encountered.

📐

Plan Errors and Omissions

Incomplete, inconsistent, or inaccurate plans and specifications may require additional work, redesign, resequencing, or changed construction methods.

🔢

Quantity Variations

Actual installed or measured quantities may vary materially from estimates, affecting production, unit cost, mobilization, materials, and equipment utilization.

🚦

Access and Work Restrictions

Lane closure limitations, restricted work windows, unavailable work areas, inspection issues, or changed access may reduce productivity and extend performance.

⚡

Acceleration

A contractor may be required to add crews, shifts, overtime, equipment, or resequencing to complete work earlier than the adjusted schedule would otherwise permit.

🛑

Suspension of Work

Written or constructive suspension may create time and cost impacts when work is stopped for a period that was not anticipated or inherent in the project.

🔌

Utility Conflicts

Unrelocated, unidentified, or inaccurately located utilities may interfere with planned operations and require additional work, standby, or resequencing.

👥

Third-Party Interference

Railroads, utility companies, other contractors, local governments, inspectors, or adjacent operations may affect access, methods, sequence, and production.

Change Orders and Disputed Work

Many project issues can be resolved through the change order process. A claim may develop when the parties cannot agree on entitlement, cost, time, or the complete effect of the change.

🤝

Bilateral Change Orders

A bilateral change order is used when the parties agree on the change and its effect on compensation, contract time, or other contract terms.

The contractor should review release language to confirm whether the change order resolves only the stated work or also waives broader impacts.

1️⃣

Unilateral Change Orders

VDOT may issue a unilateral change order when a contract change is required but the parties do not agree on all cost, time, or contractual impacts.

Acceptance of payment or continued performance should not unintentionally waive properly preserved disputed amounts.

🧮

Force Account Work

When scope or price cannot be agreed in advance, work may be tracked based on actual labor, materials, equipment, and allowable additions.

Accurate daily records and timely comparison with inspector records are especially important.

✍️

Reservation of Rights

A contractor should clearly identify unresolved time, productivity, overhead, quantity, and cumulative impacts before signing a change order or release.

A general reservation may be less effective than a specific identification of unresolved issues.

A change order may resolve more than the direct cost of the changed work. Before signing, contractors should determine whether the document releases delay, disruption, extended overhead, acceleration, cumulative impact, or other related claims.

Delay, Disruption, and Acceleration Claims

Time-related claims require more than evidence that the project finished later or cost more than expected. The contractor must connect the occurrence to actual schedule and cost impacts.

Type of Impact Potential Cause Important Documentation
Critical delay Late access, design changes, utility conflicts, suspension, inspection, or unavailable work areas Baseline schedule, updates, critical path analysis, daily reports, notices, and directives
Disruption Fragmented work, resequencing, trade interference, changing work areas, or repeated mobilization Production records, planned versus actual comparisons, crew reports, and contemporaneous correspondence
Acceleration Required completion without an appropriate extension of time or direction to increase resources Schedule requests, denied extensions, directives, overtime, added crews, and equipment records
Extended overhead Compensable extension of the project duration Project staffing, field costs, equipment, facilities, accounting records, and schedule analysis
Standby Labor or equipment remains available but cannot perform planned work Equipment ownership or rental records, daily reports, availability, and mitigation efforts
Seasonal impact Compensable delay pushes work into less productive weather, traffic, or environmental conditions Original schedule, weather records, production data, and causal schedule analysis

A schedule impact analysis may be required by the contract for time-related changes or claims. The applicable specifications and project-specific provisions should be reviewed early.

Quantity and Unit-Price Disputes

Highway projects frequently use unit-price compensation based on measured or accepted quantities. Disputes may arise over measurement, classification, acceptance, significant variation, or whether work is included in another pay item.

📏

Measurement Methods

The contract may use plan quantities, field measurement, weight, volume, area, installed units, or another defined method for determining payment.

🧮

Quantity Calculations

Survey records, tickets, inspection records, measurements, photographs, and calculation sheets may be necessary to establish the quantity performed.

📦

Included or Incidental Work

VDOT may contend that disputed work is included in another pay item or incidental to the contract rather than separately compensable.

📈

Significant Increases

A major increase may affect production, sourcing, labor, equipment, and whether the original unit price fairly reflects the changed work.

📉

Significant Decreases

A major decrease may prevent recovery of mobilization, overhead, committed material, equipment, or other costs expected to be spread across estimated quantities.

✅

Acceptance Disputes

Payment may depend on testing, inspection, documentation, specification compliance, and formal acceptance of the completed work.

Subcontractor Claims on VDOT Projects

Subcontractors generally do not have a direct contract with VDOT. Their project claims commonly must be presented through the prime contractor under the subcontract and prime contract procedures.

Preserving a Pass-Through Claim

The subcontractor must address its own subcontract requirements while providing the prime contractor what it needs to preserve and present the claim to VDOT.

  • Provide prompt written notice to the prime contractor
  • Identify any VDOT notice or claim deadline
  • Request that the prime contractor submit the required NOI
  • Document labor, materials, equipment, quantities, and time
  • Provide schedule and cost support
  • Confirm how the prime contractor will present the claim
  • Reserve rights in change orders and payment releases
  • Track the status of the claim and any VDOT response
🔁

Prime Contractor Cooperation

The subcontract should address whether the prime contractor must:

  • Sponsor qualifying subcontractor claims
  • Submit required notices to VDOT
  • Include the claim in administrative proceedings
  • Provide relevant project documents
  • Keep the subcontractor informed
  • Allow participation in claim preparation
  • Distribute any recovery fairly
A subcontractor should not assume that the prime contractor preserved the claim. The subcontractor should confirm in writing whether the required VDOT notice was submitted and whether its costs and time impacts are included.

Documents That Support a VDOT Claim

Contemporaneous records are often more persuasive than explanations reconstructed after the work is complete.

📁

Contract and Notice Documents

  • Prime contract and subcontract
  • Plans, specifications, and special provisions
  • Notices of Intent to File a Claim
  • Change order requests and responses
  • Directives, RFIs, and correspondence
  • Meeting minutes and inspection records
  • Reservations of rights
📊

Cost and Impact Documents

  • Daily work reports
  • Labor and certified payroll records
  • Equipment records
  • Material invoices and delivery tickets
  • Quantity and measurement records
  • Baseline schedules and updates
  • Photographs and videos
Daily comparison matters. When additional work is being tracked on an actual-cost basis, contractors should compare labor, equipment, material, and quantity records with the project inspector's records and address differences promptly.

VDOT Administrative Claim Process

Unresolved project issues may proceed from an NOI and change order dispute to a formal administrative claim under the contract, VDOT specifications, and Virginia law.

1

Occurrence and Notice

The contractor provides a timely written NOI at the occurrence or before beginning the disputed work and complies with any additional contract-specific notice requirements.

2

Project-Level Review

The parties evaluate entitlement, cost, time, documentation, and whether the issue can be resolved through a bilateral or unilateral change order.

3

Optional NOI Escalation

Unresolved NOI issues may be discussed through the project and district escalation procedures described by VDOT before final claim submission.

4

Certified Written Claim

The contractor submits its certified written claim within the required period after the final estimate date, with facts, entitlement, impact, quantification, and proof of timely NOI.

5

Department Decision

VDOT investigates and issues a written decision. The statutory process allows limited extensions by mutual agreement.

6

Commissioner Review and Further Action

A dissatisfied contractor must preserve the next level of administrative review and any subsequent legal action within the applicable deadlines.

The formal claim is tied to the final estimate date. Under Virginia Code § 33.2-1101, the contractor generally must deliver its written claim within 60 days after the final estimate date identified by VDOT. A claim submitted before that date or more than 60 days afterward may be rejected as untimely.

When to Contact a VDOT Claims Attorney

Counsel can provide the greatest value while the occurrence is developing and before notice, documentation, or change order decisions are finalized.

  • VDOT or the prime contractor directed changed work
  • The parties disagree about price or contract time
  • Field conditions differ from the project documents
  • A utility or third party is interfering with performance
  • Work is delayed, suspended, or resequenced
  • An extension of time has been denied
  • You are being required to accelerate
  • A subcontractor has submitted a pass-through claim
  • A change order contains broad release language
  • The final estimate date is approaching
⚖️

Project-Focused Claims Counsel

We help contractors evaluate the legal and practical requirements of a claim while the project records and available remedies can still be protected.

  • Contract and specification review
  • NOI preparation and evaluation
  • Change order and release review
  • Claim documentation strategy
  • Administrative claim preparation
  • Negotiation and litigation support

Related Government Construction Services

VDOT claims often overlap with subcontract review, payment disputes, retainage, backcharges, and payment bond rights.

🏛️

Government Construction Counsel

Representation for contractors and subcontractors working on Virginia public and infrastructure projects.

Explore Government Construction Services

📄

Government Subcontract Review

Review and negotiation of VDOT, highway, state, local, and federal construction subcontracts.

Explore Subcontract Review Services

💵

Payment and Bond Claims

Assistance with unpaid invoices, retainage, backcharges, VDOT nonpayment, and payment bond claims.

Explore Payment Claim Services

Frequently Asked Questions

The applicable requirements depend on the contract, specifications, delivery method, project-specific provisions, occurrence, and claimant's position in the contracting chain.

What is a VDOT Notice of Intent to File a Claim?

An NOI is written notice that a contractor intends to seek additional compensation, time, or another contract adjustment based on an occurrence or disputed work. It gives VDOT an opportunity to review and potentially mitigate or resolve the issue.

When must a VDOT NOI be submitted?

A contractor generally must submit an NOI at the time of the occurrence or before beginning the work upon which the claim will be based. Additional notices may also be required by the specifications or project documents.

Does a change order request count as an NOI?

Not necessarily. VDOT guidance explains that change notices, meetings, and requests for contract modification do not automatically satisfy the separate NOI requirement. The notice should expressly state that it is a Notice of Intent to File a Claim.

Can a subcontractor submit a claim directly to VDOT?

A subcontractor generally lacks a direct contract with VDOT. Its project claim will commonly need to be preserved and presented through the prime contractor under the subcontract, prime contract, and VDOT procedures.

What must a VDOT claim establish?

A supported claim generally must demonstrate compliance with required procedures, contractual entitlement, impact on cost or time, causation, and reliable quantification of the requested adjustment.

How long does a contractor have to submit a formal VDOT claim?

Under Virginia Code § 33.2-1101, the contractor generally must deliver its written claim within 60 days after the final estimate date established by VDOT. Timely written notice of intent must also have been provided at the occurrence or beginning of the work supporting the claim.

What is the difference between a bilateral and unilateral change order?

A bilateral change order reflects agreement on the change and its contract impacts. VDOT may issue a unilateral change order when a change is required but the parties do not agree on all cost, time, or contractual effects.

What records should be kept for extra work?

The contractor should maintain daily labor, equipment, material, quantity, production, schedule, photograph, directive, and correspondence records. Those records should be compared with project inspector records when required or practical.

Should a contractor sign a disputed change order?

The contractor should review the change order's pricing, time adjustment, release, and reservation language. Signing without a specific reservation may waive unresolved delay, disruption, overhead, quantity, or cumulative impact claims.

Get Help With a VDOT or Highway Construction Claim

If your company is dealing with changed work, differing conditions, delay, acceleration, disputed quantities, a denied change order, or an unresolved subcontractor claim, we can review the project documents and help protect the available claim.